2. Access the “Scheduler Options” section. Within this section, the scheduler can be enabled, run mode selected,
and load mode selected.
3. Access the “Scheduler Setup” section. Within this section, each schedule entry can be modified by pressing the
Enter “” button to select the item and the up “” and down “” arrows to define them.
Note: The controller must be in “Auto Mode” to run at the programmed time. Use a trickle or solar battery charger
to prevent the controller from draining the battery while in “Auto Mode.”
SET THE UNIT TO AUTO MODE
1. From any Operator or Maintenance screen, press and hold the Auto/Manual Mode button for five seconds, or
until the “AUTO” icon is shown on the main display.
Note: If any of the scheduled time slots are currently active, the controller will begin the starting sequence and start
the unit provided there are no shutdown conditions present.
“AUTO” (REMOTE) STARTING OF THE GENERATOR
“Auto Mode” is used when the generator is started from a location other than the control panel by using a transfer
switch. “AUTO” (remote start) is the normal setting when the generator is being used as a standby power supply.
Before putting the generator in the “AUTO” mode, review the Prestart Checklist and Manual Starting of the Generator
on page 25. Also follow all safety warnings and information on isolating the generator with a transfer switch if the
unit is to be used as a standby power supply. Refer to “PreStart Checklist” on page 25. Then continue with the steps
described below:
1. Perform a manual start of the generator at least once to verify that the engine is operating correctly.
2. If a check of the remote start circuit is desired, remove the wires from the remote start terminal block.
Press the Auto/Manual Mode button, the main display should show the “AUTO” icon. Attach a jumper
wire (minimum 16 gauge) across the two terminals on the remote start terminal block. This applies a
ground to the Power Zone™ Controller to close the starting circuit contacts. The engine should crank,
start and run.
3. Remove the jumper wire from the remote start terminal block and the engine will stop. Reconnect any
necessary wires from the remote start switch (transfer switch) to the remote start terminal block.
4. Confirm unit is in “Auto Mode.” The main display should show “Auto Mode” at the top of the screen.
5. Close the main circuit breaker (set to “ON/I”).
6. Secure the generator by closing and locking all access doors.
7. The generator is now ready for remote starting.
Item Values
Enable Yes/No
Run Mode Monthly/Weekly
Load Idle, In Island, On Load, Off Load
Item Values
Schedule Entry 1-16
Start Time 00:00-23:59
Duration 00:00-99:59
Day Monday-Sunday
Week (of month) First, Second, Third, Fourth